Station Update
August 2008
The new Fire Station No. 1 is open for business! Edina’s Mayor, City Council
members, Fire Department personnel, other City staff and elected officials were
on hand with members of the public for the July 31 ribbon-cutting ceremony
celebrating the opening of the newly constructed Fire Station No. 1.
Edina
Fire Chief Marty Scheerer kicked off the ribbon cutting ceremony by introducing
elected officials, City Manager Gordon Hughes, Mayor Jim Hovland and other
distinguished guests. Hovland spoke praises of the new station before boarding a
fire truck with Council Member Ann Swenson’s 4-year-old grandson, Jack, and
driving through the red ribbon tied across the doors of the new Fire Station’s
apparatus bay – officially declaring its opening.

Those present were invited inside to enjoy cake and
refreshments, as well as receive informal tours of the nearly completed station.
In addition to making up for many of the shortcomings in the old station, this
new fire station will give Edina the opportunity to grow and expand the Fire
Department in the future. It will serve as a great benefit to the community and
help ensure that Edina’s Fire Department is able to provide unmatched service
and one of the quickest response times in the metro area.
The
month of August was spent finishing the move into the new Station. Contractors
are still making finishing touches to the interior of the building, but the Fire
Department has been able to maintain their normal routine while working around
them. All Chief Officers, Administration and Fire Prevention Bureau staff have
moved into their new offices. Shifts began working out of the station early in
the month. The public is invited to tour the new facility during the Fire
Department’s Annual Open House held the afternoon of Sunday, Oct. 12.
Building
the new fire station has been a long and sometimes challenging process, but the
City and Fire Department are happy to have it nearly complete and look forward
to using it to serve the community for years to come.
July 2008
The Edina Fire Department (EFD) began moving into the new fire Station No. 1
on June 30, 2008. It is a fantastic building that will meet the Department’s
needs as well as the community’s well into the future.
July was spent moving furniture and equipment into the
building and beginning to get things operational. Only select staff members have
moved into their new offices, as the contractor’s are finishing up the interior,
but most staff should be moved-in by Aug. 1.
A ribbon cutting ceremony celebrating the opening of the
station is set to take place on Thursday, July 31, 2008 at 5 p.m.
The
new station is a much needed addition to the community. The old fire station was
built in 1969 and was designed to house four to five male firefighters and three
other administrative staff -- it had no accommodations for female firefighters.
It was also only able to hold three to four large firefighting vehicles and did
not have the proper capacity to function as a paramedic ambulance service, which
was not in existence in 1969.
In 1975, the Fire Department began its paramedic ambulance
service. The volume of emergency calls over the years made hiring additional
firefighter/paramedics a necessity. The Fire Department itself also grew in
function. Beyond fighting fires, EFD now responds to all rescue calls, hazmat
incidents, emergency medical calls, ice rescues, water rescues, trench rescues,
high angle rescues and many other emergencies. Today, additional
firefighter/inspectors are also needed to inspect all new and existing
commercial construction. Actual fires now represent less than five percent of
emergency calls.
Additions
and renovations to the old station were frequent during the last 35+ years in an
attempt to transform the building into a usable work environment. Shortcomings
including several OSHA, Building Code, Fire Code, ADA and HIPPA violations made
the building difficult to operate from. In addition to design constraints, the
building was also plagued with mold problems.
Studies looking into remodeling the building resulted in
very expensive and unsatisfactory results. The second option was to leave the
existing garage space and rebuild the main part of the station. Again, this was
an expensive option that did not meet all current and future needs. Finally, it
was determined that the cost of building a completely new building would only
add an additional 15 percent to the cost of remodeling -- and was far more
desirable in meeting current and future requirements.
The new building has several things the old fire station
did not have, including:
- Women’s locker room
- Individual sleeping
quarters
- Fitness room
- Training room

- Meeting/conference rooms
- Adequate office space
- Secure narcotics storage
space
- Secure medical records
storage space
- Adequate general storage
space
- Room for 12 large vehicles
- Medical clean room
- Medical supply storage
room
- Adequate locker room space
for male firefighters
- White roof to reduce
cooling costs
- Clean water system for
water run-off
- High efficiency heating
and cooling systems
- Automatic back-up
electrical generator that will also be used for Energy Savings Program with
Xcel
- Fire sprinkler system
- Fire alarm system
- SCBA Room
- Fire Prevention plan
review area
These improvements, along with almost double the square
footage of the old station, will allow for continued efficient operation of the
Fire Department and accommodate any future growth.
EFD will also be holding its annual Open House on Sunday,
October 12, from 12:30 - 4:30 p.m. at the new Fire Station No. 1. Hope to see
you there!
June 2008
The progress at Fire Station No. 1 has been very encouraging since April.
The weather has been cooperative and the building is nearing completion. As of
the first week in June, the exterior is 99 percent complete. The interior is
being painted, ceilings and lights are being installed, electrical work is being
completed, tile is nearly complete and the building is completely weather tight.
The project continues to remain on budget and the contractor is scheduled to
finish construction by the end of June. Landscaping work will continue through
July. A delay in shipping furniture has occurred because the supplier of
laminate materials no longer ships orders until they have a full truck due to
high fuel costs. Furniture should now be shipped in early July.
Fire Department personnel still plan on moving into Fire Station No. 1, even
without all of the furniture. It is estimated to take about two weeks to be
moved in and fully operational. Temporary facilities will continue to be staffed
until the Department is able to operate out of the new fire station.
The building is going to be a magnificent addition to the City and will
significantly improve the Fire Department in numerous ways for many years. The
support of the community throughout this project has been much appreciated.
April 2008
The Fire Station No. 1 construction project is moving along. The windows are
being installed and the white roof is complete. The main building will be
weather-tight very soon. The tall wall in the front of the building will be clad
with copper before long.
There have been some weather-related delays such as high
winds when the roof planks were scheduled to be installed, snow when the white
roof was scheduled to be installed and, of course, all the mud around the
building from the ground frost thawing. There were also some drawing errors by
the architect and soil corrections that created some delays in construction.
The next big step in the project is to have the concrete
apparatus floor poured and finished. The apparatus floor has an abundance of
plumbing, electrical conduits and an in-floor heating system. The in-floor heat
system warms the concrete floor which has a large thermal mass and retains the
heat as vehicles move in and out of the fire station. The radiant heat from the
floor heats the vehicles, not the air, and is the most energy efficient type of
heating system.
The building is really starting to look like a fire station
and the project remains on budget. The Fire Station will be an outstanding
addition to the community when it is complete, which is now scheduled for June
2008.
February 2008
Construction is moving along well at the Fire Station site. There were some
difficult days in January when the temperatures were well below zero. There was
also a three-day delay in installing the roof planks on the second level with
the crane due to high wind conditions.
The concrete plank roof is now installed on all areas except the second level
stairways. The stairways should be completed the second week of the
month. Having the building covered will help with the construction pace. The
actual “white roof” should be installed by the end of February if all goes
well. The “white roof” is an energy-saving composite material that reflects the
heat off the roof and reduces the energy needed to keep the building cool in the
summertime. There are also several skylights that will provide natural light to
much of the building, thus reducing our electrical energy demand for lighting.
The north end of the building has nearly all of the exterior brick installed
and they will be removing the plastic and scaffolding the first week of the
month.
The project remains on schedule and on budget.
December 2007
Construction
is moving along at Fire Station No. 1. The roof was installed on the apparatus
area on Dec. 20. The roof should be installed on the second level of the main
building in mid-January. Although covered with plastic to keep warm and not
visible from the exterior, the brick is being installed on the outside of the
building. Fortunately, most of the interior walls are finished block; therefore,
there will be much less finish work on the interior than most buildings. The
Department is still anticipating a May 2008 completion date. The project remains
within budget.
September 2007
The following was submitted as an editorial in the Edina Sun-Current:
For over 45 years, the Edina community has supported the Edina Fire Department.
With the construction of the new fire station at 6250 Tracy Ave. under way, it
is important, and only proper, that we keep residents informed of its progress
and reassure everyone that even during construction we are well-positioned
throughout the City.
Temporarily deployed in four locations throughout Edina, emergency run times
have remained consistent prior to and throughout the construction process. With
firefighters stationed at Fire Station No. 2, 7335 York Ave.; a construction
trailer at Edina’s Public Works Building, 5146 Eden Ave.; a warehouse at 6801
Washington Ave.; and the South Metro Public Safety Training Facility, 7525
Braemar Blvd.; run times the past six months have averaged four minutes, thirty
seconds.
The Edina Fire Department began the project of rebuilding Fire Station No. 1 on
May 1. The first two weeks of May were spent clearing out the asbestos that was
used as installation during the construction of the old station in 1969. The
project was then handed over to the contractor and old Fire Station No. 1 was
torn down.
Through May and June, the project moved along smoothly until it was discovered
that the soil below the old station contained large amounts of clay and needed
to be corrected before further digging could continue. The clay was removed and
replaced with sand, which will eventually improve the water-proofing of the
building and ensure proper water drainage outside the walls.
With the soil contents corrected and the basement drains in place, the
contractors were set to pour the concrete floor when the first rain of the
summer started coming down. Forced to wait out the storm, construction workers
then had to dig out the wet soil in the basement and replace it with dry soil.
Rain continued to plague construction, as workers attempted to place footings
around the building. Complicating the work further was the fact that the lot
size is too small to work on both the main building footings and apparatus
footings at the same time. Construction workers were required to dig footings
for the main building and place those before working on the footings for the
apparatus floor.
There was also a communication error by one of the sub-contractors with a
supplier. They failed to order the correct block color for the new building and
there was a delay in receiving the correct block.
Construction crews are now focusing on establishing the block walls of the main
building of the new Fire Station. The contractor has doubled up construction
crews to make up for time lost due to rain and other minor hiccups.
As with any construction project, we have experienced delays in the building
process, but the Fire Department is staying positive.
The City has given the contractor one year from the start date of the project to
complete the new station. Though the contractor originally asserted that the
station will only take nine months to complete, the City is confident that the
project will be done within the one-year time frame. There is a significant
financial penalty assessed to the contractor if the station is not complete by
May 12, 2008.
On behalf of all the men and women of the Edina Fire Department, thank you for
your ongoing support.
August 2007
The basement has been capped with the concrete planking. The
contractors are now back-filling around the basement and then they will begin
working on installing the footings for the remainder of the building once all
the soil has been back-filled. The footings had to be completed in two stages
due to the small site and no location for all of the soil that needed to be
moved to put in the footings.
July 2007
The project has been delayed for a week, following recent
rainfalls. At the time the rain fell, the basement soils and drains were ready
for the concrete floor to be poured. The water created poor soil conditions and
the contractor had to remove the wet soil and floor drains and replace them once
the ground was dry. The plan is now to pour concrete on Monday July 23. The
basement roof will follow shortly thereafter.
June 2007: The large cottonwood tree located at 6250 Tracy Ave. recently was
taken down. The City Forrester evaluated the tree and determined that, due to
rot and decay, the tree was no longer healthy and posed potential danger to
pedestrians and cars.
May 2007: The Edina Fire Department has moved out of Fire Station No. 1, 6250
Tracy Ave.
Six firefighter/paramedics are working out of Fire Station No. 2, 7330 York
Ave. The other two members of the shift are located in a construction trailer
parked under the parking garage at Public Works, 5146 Eden Avenue.
Fire Department Administration and Fire Prevention have moved to the
Southwest corner of the City. The Fire Prevention Team is working out of the
South Metro Training Facility, 7525 Braemar Blvd. The four share office space in
the back left corner of the building. Other administrative personnel are working
out of a warehouse located across Hwy. 169 at 6801 Washington Ave.
The building at 6250 Tracy has undergone asbestos removal.
The building at 6250 Tracy has been demolished.
|