Station Update
June 2008
The progress at Fire Station No. 1 has been very encouraging since April.
The weather has been cooperative and the building is nearing completion. As of
the first week in June, the exterior is 99 percent complete. The interior is
being painted, ceilings and lights are being installed, electrical work is being
completed, tile is nearly complete and the building is completely weather tight.
The project continues to remain on budget and the contractor is scheduled to
finish construction by the end of June. Landscaping work will continue through
July. A delay in shipping furniture has occurred because the supplier of
laminate materials no longer ships orders until they have a full truck due to
high fuel costs. Furniture should now be shipped in early July.
Fire Department personnel still plan on moving into Fire Station No. 1, even
without all of the furniture. It is estimated to take about two weeks to be
moved in and fully operational. Temporary facilities will continue to be staffed
until the Department is able to operate out of the new fire station.
The building is going to be a magnificent addition to the City and will
significantly improve the Fire Department in numerous ways for many years. The
support of the community throughout this project has been much appreciated.
April 2008
The Fire Station No. 1 construction project is moving along. The windows are
being installed and the white roof is complete. The main building will be
weather-tight very soon. The tall wall in the front of the building will be clad
with copper before long.
There have been some weather-related delays such as high
winds when the roof planks were scheduled to be installed, snow when the white
roof was scheduled to be installed and, of course, all the mud around the
building from the ground frost thawing. There were also some drawing errors by
the architect and soil corrections that created some delays in construction.
The next big step in the project is to have the concrete
apparatus floor poured and finished. The apparatus floor has an abundance of
plumbing, electrical conduits and an in-floor heating system. The in-floor heat
system warms the concrete floor which has a large thermal mass and retains the
heat as vehicles move in and out of the fire station. The radiant heat from the
floor heats the vehicles, not the air, and is the most energy efficient type of
heating system.
The building is really starting to look like a fire station
and the project remains on budget. The Fire Station will be an outstanding
addition to the community when it is complete, which is now scheduled for June
2008.
February 2008
Construction is moving along well at the Fire Station site. There were some
difficult days in January when the temperatures were well below zero. There was
also a three-day delay in installing the roof planks on the second level with
the crane due to high wind conditions.
The concrete plank roof is now installed on all areas except the second level
stairways. The stairways should be completed the second week of the
month. Having the building covered will help with the construction pace. The
actual “white roof” should be installed by the end of February if all goes
well. The “white roof” is an energy-saving composite material that reflects the
heat off the roof and reduces the energy needed to keep the building cool in the
summertime. There are also several skylights that will provide natural light to
much of the building, thus reducing our electrical energy demand for lighting.
The north end of the building has nearly all of the exterior brick installed
and they will be removing the plastic and scaffolding the first week of the
month.
The project remains on schedule and on budget.
December 2007
Construction
is moving along at Fire Station No. 1. The roof was installed on the apparatus
area on Dec. 20. The roof should be installed on the second level of the main
building in mid-January. Although covered with plastic to keep warm and not
visible from the exterior, the brick is being installed on the outside of the
building. Fortunately, most of the interior walls are finished block; therefore,
there will be much less finish work on the interior than most buildings. The
Department is still anticipating a May 2008 completion date. The project remains
within budget.
September 2007
The following was submitted as an editorial in the Edina Sun-Current:
For over 45 years, the Edina community has supported the Edina Fire Department.
With the construction of the new fire station at 6250 Tracy Ave. under way, it
is important, and only proper, that we keep residents informed of its progress
and reassure everyone that even during construction we are well-positioned
throughout the City.
Temporarily deployed in four locations throughout Edina, emergency run times
have remained consistent prior to and throughout the construction process. With
firefighters stationed at Fire Station No. 2, 7335 York Ave.; a construction
trailer at Edina’s Public Works Building, 5146 Eden Ave.; a warehouse at 6801
Washington Ave.; and the South Metro Public Safety Training Facility, 7525
Braemar Blvd.; run times the past six months have averaged four minutes, thirty
seconds.
The Edina Fire Department began the project of rebuilding Fire Station No. 1 on
May 1. The first two weeks of May were spent clearing out the asbestos that was
used as installation during the construction of the old station in 1969. The
project was then handed over to the contractor and old Fire Station No. 1 was
torn down.
Through May and June, the project moved along smoothly until it was discovered
that the soil below the old station contained large amounts of clay and needed
to be corrected before further digging could continue. The clay was removed and
replaced with sand, which will eventually improve the water-proofing of the
building and ensure proper water drainage outside the walls.
With the soil contents corrected and the basement drains in place, the
contractors were set to pour the concrete floor when the first rain of the
summer started coming down. Forced to wait out the storm, construction workers
then had to dig out the wet soil in the basement and replace it with dry soil.
Rain continued to plague construction, as workers attempted to place footings
around the building. Complicating the work further was the fact that the lot
size is too small to work on both the main building footings and apparatus
footings at the same time. Construction workers were required to dig footings
for the main building and place those before working on the footings for the
apparatus floor.
There was also a communication error by one of the sub-contractors with a
supplier. They failed to order the correct block color for the new building and
there was a delay in receiving the correct block.
Construction crews are now focusing on establishing the block walls of the main
building of the new Fire Station. The contractor has doubled up construction
crews to make up for time lost due to rain and other minor hiccups.
As with any construction project, we have experienced delays in the building
process, but the Fire Department is staying positive.
The City has given the contractor one year from the start date of the project to
complete the new station. Though the contractor originally asserted that the
station will only take nine months to complete, the City is confident that the
project will be done within the one-year time frame. There is a significant
financial penalty assessed to the contractor if the station is not complete by
May 12, 2008.
On behalf of all the men and women of the Edina Fire Department, thank you for
your ongoing support.
August 2007
The basement has been capped with the concrete planking. The
contractors are now back-filling around the basement and then they will begin
working on installing the footings for the remainder of the building once all
the soil has been back-filled. The footings had to be completed in two stages
due to the small site and no location for all of the soil that needed to be
moved to put in the footings.
July 2007
The project has been delayed for a week, following recent
rainfalls. At the time the rain fell, the basement soils and drains were ready
for the concrete floor to be poured. The water created poor soil conditions and
the contractor had to remove the wet soil and floor drains and replace them once
the ground was dry. The plan is now to pour concrete on Monday July 23. The
basement roof will follow shortly thereafter.
June 2007: The large cottonwood tree located at 6250 Tracy Ave. recently was
taken down. The City Forrester evaluated the tree and determined that, due to
rot and decay, the tree was no longer healthy and posed potential danger to
pedestrians and cars.
May 2007: The Edina Fire Department has moved out of Fire Station No. 1, 6250
Tracy Ave.
Six firefighter/paramedics are working out of Fire Station No. 2, 7330 York
Ave. The other two members of the shift are located in a construction trailer
parked under the parking garage at Public Works, 5146 Eden Avenue.
Fire Department Administration and Fire Prevention have moved to the
Southwest corner of the City. The Fire Prevention Team is working out of the
South Metro Training Facility, 7525 Braemar Blvd. The four share office space in
the back left corner of the building. Other administrative personnel are working
out of a warehouse located across Hwy. 169 at 6801 Washington Ave.
The building at 6250 Tracy has undergone asbestos removal.
The building at 6250 Tracy has been demolished.
|